Week of March 27 -April 2
Gabriel Mendoza:
1. Completed settings panel
Enrique Vaca:
Week of April 3 - 9
Gabriel Mendoza:
1. Completed brightness settings
2. Bug fixes
Enrique Vaca:
Week of April 10 - 16
Gabriel Mendoza:
1. Worked on traffic settings, misc bug fixes
Enrique Vaca:
Week of April 16 - 18
Gabriel Mendoza:
1 . Completed traffic settings
2. Completed doorbell settings
Enrique Vaca:
Abeer Alsaiari:
Gabriel Mendoza:
- Completed Volume
1. Completed settings panel
Enrique Vaca:
- Completed Restart feature
- Completed Traffic feature
- Main Interface design for the door and Home button panel
- Completed Multi users from inside
- Completed Initial Door Events from Inside and Outside
Week of April 3 - 9
Gabriel Mendoza:
- Completed Number Pad
- Completed Finger Print
1. Completed brightness settings
2. Bug fixes
Enrique Vaca:
- Completed News feature
- Completed Transport feature
- Completed Dead bolt
- Completed To do list
- Completed Camera
- Complete Height Adjustment for the Door Application
Week of April 10 - 16
Gabriel Mendoza:
- Worked on Languages
- Worked on Date/Time
1. Worked on traffic settings, misc bug fixes
Enrique Vaca:
- Completed Alarm feature
- Completed Lights feature
- Completed Mirror feature
- Worked on Messages
Week of April 16 - 18
Gabriel Mendoza:
- Completed Languages
- Completed Two verification
- Completed Date/Time
1 . Completed traffic settings
2. Completed doorbell settings
Enrique Vaca:
- Worked on App Description Website
- Made the project video
- Unsucessfully worked on Messages. Completed by Abeer, the real MVP.
Abeer Alsaiari:
- Completed what Enrique started with messages
- Completed the front end of Date/Time and Language Settings
- Completed the Emergency
- Completed the Themes Settings
- Completed the Users Settings
- Completed the Tutorial